Project Title |
Award Amount |
Project Acceptance |
|
|
1
|
2
|
10
|
0333
|
KEKUANAOA BUILDING - BASEMENT EWA SIDE RENOVATION
|
$145,000
|
12/16/04
|
|
1
|
2
|
11
|
7157
|
DEPT OF AGRICULTURE FACILITY - AGRI & CONSERV BLDG A, STRUCT REPAIRS & REROOFING
|
$331,152
|
12/10/04
|
|
1
|
2
|
11
|
7144
|
DOA MAIN OFFICE COMPLEX - ELECTRICAL AND FIRE SAFETY IMPROVEMENTS
|
$151,009
|
12/10/04
|
|
1
|
2
|
20
|
2579
|
HAWAII STATE HOSPITAL - GUENSBERG BUILDING, VARIOUS IMPROVEMENTS
|
$319,799
|
12/06/04
|
|
6
|
2
|
10
|
0361
|
CAPITOL CENTER BUILDING - INSTALL SLIDING DOORS
|
$24,000
|
12/06/04
|
|
6
|
2
|
10
|
0357
|
ARCHIVES STORAGE (RECORDS CENTER) - INSTALL FIRE SPRINKLER
|
$182,888
|
11/29/04
|
|
1
|
2
|
36
|
6330
|
PEARL CITY PUBLIC LIBRARY - ACCESSIBILITY AND OTHER IMPROVEMENTS
|
$111,453
|
11/19/04
|
|
1
|
2
|
36
|
6340
|
HAWAII KAI PUBLIC LIBRARY - REROOF
|
$238,800
|
11/15/04
|
|
1
|
1
|
21
|
7142
|
HILO JUDICIARY COMPLEX - DEMOLITION OF KAIKOO MALL
|
$2,254,000
|
11/04/04
|
|
1
|
2
|
14
|
7148
|
STATE CIVIL DEFENSE - BIRKHIMER TUNNEL, SECURE ROOM
|
$111,800
|
11/02/04
|
|
1
|
2
|
21
|
7127
|
KAPUAIWA BUILDING - INTERIOR ALTERATIONS AND IMPROVEMENTS
|
$273,300
|
10/29/04
|
|
1
|
2
|
36
|
6338
|
LILIHA PUBLIC LIBRARY - REPAIR ROOF AND CEILING
|
$364,222
|
10/26/04
|
|
6
|
2
|
10
|
0293
|
Capitol Center Building - Replace Air Conditioning Chiller
|
$356,400
|
10/22/04
|
|
1
|
2
|
21
|
7128
|
JUVENILE DETENTION HOME FACILITY - ROOFING AND OTHER IMPROVEMENTS
|
$328,809
|
10/11/04
|
|
1
|
2
|
36
|
6327
|
MCCULLY-MOILIILI PUBLIC LIBRARY - ACCESSIBILITY AND OTHER IMPROVEMENTS
|
$47,500
|
10/07/04
|
|
1
|
2
|
36
|
6331
|
KANEOHE PUBLIC LIBRARY - ACCESSIBILITY AND OTHER IMPROVEMENTS
|
$124,800
|
10/03/04
|
|
1
|
2
|
31
|
4057
|
UH MANOA - ELECTRICAL POWER DISTRIBUTION SYSTEM, PH. IV
|
$2,897,474
|
09/30/04
|
|
1
|
2
|
21
|
7134
|
KAAHUMANU HALE - A/C CHILLER REPLACEMENT AND OTHER IMPROVEMENTS
|
$1,003,885
|
09/30/04
|
|
6
|
5
|
10
|
0291
|
WAILUKU STATE OFFICE BUILDING - REPLACE FIRE SPRINKLER IN GARAGE
|
$39,360
|
09/14/04
|
|
1
|
1
|
31
|
4132
|
UNIVERSITY OF HAWAII AT HILO - UTILITY GRID, PHASE II
|
$1,797,800
|
08/31/04
|
|
1
|
2
|
36
|
6345
|
CENTRAL DISTRICT PUBLIC LIBRARIES - HEALTH AND SAFETY IMPROVEMENTS
|
$46,380
|
08/29/04
|
|
1
|
2
|
31
|
4047
|
UH MANOA, HAWAII INSTITUTE OF GEOPHYSICS - REPAIR LABORATORY WING & LECTURE HALL
|
$895,000
|
08/16/04
|
|
1
|
2
|
21
|
7071
|
KAUIKEAOULI HALE - ARCHITECTURAL BARRIER REMOVAL
|
$398,098
|
08/12/04
|
|
1
|
2
|
20
|
2580
|
DEPARTMENT OF HEALTH LABORATORY - EMERGENCY POWER UPGRADE
|
$16,740
|
08/02/04
|
|
1
|
2
|
10
|
0270
|
KEKUANAOA BUILDING - RENOVATION OF THE THIRD FLOOR CONFERENCE ROOM AND LIBRARY
|
$40,506
|
07/31/04
|
|
1
|
2
|
10
|
0319
|
919 ALA MOANA BUILDING - RENOVATION OF ROOMS 110 AND 117 FOR PSD
|
$54,650
|
07/26/04
|
|
6
|
1
|
10
|
0281
|
Keakealani Office Bldg - Replace VFT Floor Tiles
|
$31,500
|
07/16/04
|
|
1
|
2
|
36
|
6347
|
LEEWARD DISTRICT PUBLIC LIBRARIES - HEALTH AND SAFETY IMPROVEMENTS
|
$29,117
|
07/13/04
|
|
6
|
4
|
10
|
0286
|
LIHUE STATE OFFICE BUILDING - REPAIR/REPLACE VARIOUS ELECTRICAL
|
$15,238
|
07/08/04
|
|
1
|
2
|
10
|
0320
|
KEELIKOLANI BUILDING - RENOVATION OF ROOM 209 ENTRANCE AREA FOR DLIR
|
$67,300
|
07/03/04
|
|
1
|
2
|
27
|
5549
|
WOMEN'S COMMUNITY CORRECTIONAL CTR - REPL DEFECTIVE OMEGA FIRE SPRINKLER HEADS
|
$71,000
|
06/25/04
|
|
1
|
2
|
36
|
6341
|
WAHIAWA PUBLIC LIBRARY - REROOF
|
$101,450
|
06/10/04
|
|
1
|
2
|
10
|
0273
|
ALOHA STADIUM - LOWER LEVEL CONCOURSE IMPROVEMENTS
|
$812,519
|
06/01/04
|
|
1
|
2
|
20
|
2569
|
LANAKILA SENIOR CENTER - HEALTH, SAFETY, AND ACCESSIBILITY IMPROVEMENTS
|
$70,000
|
05/23/04
|
|
1
|
2
|
36
|
6329
|
AIEA PUBLIC LIBRARY - ACCESSIBILITY AND OTHER IMPROVEMENTS
|
$70,000
|
05/03/04
|
|
1
|
2
|
21
|
7138
|
JUDICIARY RECORDS MANAGEMENT FACILITY - INTERIOR ALTERATIONS AND IMPROVEMENTS
|
$73,912
|
04/30/04
|
|
1
|
2
|
21
|
7069
|
ALIIOLANI HALE - ARCHITECTURAL BARRIER REMOVAL
|
$658,688
|
04/29/04
|
|
1
|
5
|
14
|
7093
|
SCD, MAUI, MOLOKAI, & LANAI - UPGRADE DISASTER WARNING & COMMUNICATIONS DEVICES
|
$282,236
|
04/19/04
|
|
1
|
2
|
33
|
7132
|
HAWAII YOUTH CORRECTIONAL FACILITY - GYMNASIUM RENOVATION
|
$132,000
|
04/16/04
|
|
1
|
2
|
36
|
6344
|
HONOLULU DISTRICT PUBLIC LIBRARIES - HEALTH AND SAFETY IMPROVEMENTS
|
$122,000
|
04/13/04
|
|
1
|
2
|
36
|
6342
|
LIBRARY FOR THE BLIND AND PHYSICALLY HANDICAPPED - REROOF
|
$92,868
|
04/10/04
|
|
1
|
1
|
14
|
7110
|
HAWAII STATE CIVIL DEFENSE - DISASTER WARNING & COMMUNICATIONS DEVICES, HAWAII
|
$332,360
|
04/08/04
|
|
1
|
2
|
10
|
0262
|
KEKUANAOA BUILDING - BALANCE AIR DISTRIBUTION SYSTEM
|
$138,272
|
04/08/04
|
|
1
|
1
|
14
|
7094
|
STATE CIVIL DEFENSE, HAWAII - UPGRADE DISASTER WARNING & COMMUNICATIONS DEVICES
|
$103,813
|
03/29/04
|
|
1
|
2
|
31
|
4155
|
WAIKIKI AQUARIUM - IMPROVEMENTS, PHASE IA, REPAIR MAIN SEAWATER PUMP
|
$10,000
|
03/26/04
|
|
6
|
2
|
10
|
0299
|
AAFES State Office Building - Replace Air Conditioning Pumps
|
$70,000
|
02/11/04
|
|
6
|
2
|
10
|
0302
|
Central Services - Renovate Custodian Storage Warehouse
|
$67,000
|
01/29/04
|
|
1
|
5
|
14
|
7115
|
MAUI ARMY NATIONAL GUARD - PUUNENE ARMORY, OFFSITE INFRASTRUCTURE
|
$434,200
|
01/22/04
|
|
1
|
2
|
36
|
6346
|
WINDWARD DISTRICT PUBLIC LIBRARIES - HEALTH AND SAFETY IMPROVEMENTS
|
$157,170
|
01/18/04
|
|
6
|
5
|
10
|
0288
|
Maui State Annex Building - Reconstruct/Resurface Parking Lot
|
$40,208
|
01/16/04
|
|
1
|
2
|
36
|
6343
|
HSPLS LOGISTICS SUPPORT BUILDING - REROOF
|
$151,760
|
01/07/04
|
|
1
|
2
|
27
|
5552
|
OAHU COMMUNITY CORRECTIONAL CENTER - SEWER IMPROVEMENTS
|
$80,200
|
01/07/04
|
|
6
|
1
|
10
|
0282
|
KEAKELANI OFFICE BUILDING - REPLACE DOOR LOCK HARDWARE AND REKEY
|
$78,987
|
01/05/04
|
|