Request for Information (RFI) FAQ

  1. What is an RFI?
  2. Is a public notice for an RFI required?
  3. Can a purchasing agency place notice of an RFI in the newspaper?
  4. What can be addressed in an RFI?
  5. Does an RFI require a meeting?
  6. Who may be invited to respond to the RFI? Does every provider have to be invited to respond?
  7. If a provider participates in an RFI are they then excluded from responding to the solicitation?
  8. What are some ways to ensure that interested parties are aware of the RFI?
  9. What must be in an RFI?
  10. How often should we conduct an RFI?
  11. We conducted an RFI, issued an RFP, could not make an award, and plan to re-solicit the services immediately.  Do we need to issue another RFI?
  12. Is an RFI limited to the competitive (RFP) method of procurement?
  13. I heard we could issue an RFI whenever federal funds are involved and not have to conduct an RFP afterwards. Is that true?
  14. How far in advance of issuing an RFP should we conduct an RFI?
  15. Does the notice of the RFI  have to include a contact person?
  16. I have a document with additional/more specific information that is needed in order to respond to the RFI. How do I make it available?
  17. Do RFIs have to have a number and name? Can I use the same number and name as my RFP?
  18. When posting on the Procurement Notices for Solicitations website should I indicate that this is an RFI?
  19. Should I complete an attestation form? What do I do with it? Do I need to keep it?
  20. I have already posted my notice and a document with additional information. How do I post the agenda for the RFI meeting?
  21. Where can I see examples of RFIs that were previously conducted?
  22. Should a summary of the RFI results be posted?  If yes, does SPO have a website where we can post the results?
  23. We received a response to our RFI after the submittal due date.  Can we still accept it?
  24. Are RFI responses public information?

 

What is an RFI?

An RFI (Request for Information) is a tool used to gather, share and clarify information when state agencies conduct planning activities for health and human services.

******************Back to Top******************

 

Is a public notice for an RFI required?

Yes. Notice of the RFI shall be placed on the Procurement Notices System (PNS) website. It is not required to place a notice in the newspaper.

Reference section 3-142-202 (a), HAR

******************Back to Top******************

 

Can a purchasing agency place notice of an RFI in the newspaper?

Purchasing agencies have the option of placing a notice of the RFI in the newspaper in addition to posting the notice on the PNS website. When doing so, the price list for placing public and procurement notices in the newspaper shall be followed. Please refer to the pricelist for public and procurement notices.

******************Back to Top******************

 

What can be addressed in an RFI?

An RFI can address any subject relevant to a state agencies planning activities such as, the goals and objectives, target population or clients to be served, services that are necessary to reach the goal, service specifications, feasibility issues, or cost factors.

Reference section 3-142-202 (b)

******************Back to Top******************

 

Does an RFI require a meeting?

No. An RFI can be conducted via fax, e-mail or mail or any other method you choose. It can even be done via your website. Notice of the RFI must be posted on the Procurement Notices (PNS) website. See question No. 2.

******************Back to Top******************

 

Who may be invited to respond to the RFI? Does every provider have to be invited to respond?

Because an RFI shall be posted on the Procurement Notices (PNS) website, you will hopefully have a reasonable exposure to interested parties. In addition, an RFI may be sent to any knowledgeable person or entity that the purchasing agency deems advisable. Keep in mind the principle of open government. A purchasing agency would not want to invite only one or two providers if there are other providers or stakeholders interested in the target group or service. Remember also that an RFI is not just for provider input but also for input from consumers/clients/users, community groups and other interested parties.

Reference: HAR Sections 3-141-407, 3-142-202(a), 3-142-202(c), and 3-142-202(d)

******************Back to Top******************

If a provider participates in an RFI are they then excluded from responding to the solicitation?

No. Collaboration with private providers is encouraged in state planning activities to facilitate efficiency, responsiveness and organization in meeting the health and human service needs of Hawaii's people. Uncompensated provider participation is encouraged. Keep in mind that collaboration does not constitute an exemption form anti-competitive practices. See question No. 5.

Reference section 3-142-203, HAR

******************Back to Top******************

What are some ways to ensure that interested parties are aware of the RFI?

As a state agency with a history of serving a particular population or addressing a particular problem you probably have access to most of the interested parties. Some sources for reaching interested parties are: advisory groups, task forces that address the client population or the issue being addressed, professional organizations or professional publications. Private providers and other interested parties may also call state purchasing agencies for the services in which they are interested and let them know they are interested in participating in future RFI’s. Remember, placing a notice of the RFI on the PNS website is required.

******************Back to Top******************

What must an RFI include?

There are 6 elements that must be included in an RFI:

  • Name of the agency issuing the request.
  • A description of the information being sought. The more specific the questions, the more likely respondents will address the areas about which you have concerns.
  • The procedure for responding. (Place and location of a meeting, address to send comments, etc.)
  • A statement that participation is optional, and is not required to respond to any subsequent procurement.
  • A statement that neither the purchasing agency nor the interested party has any obligation under the request for information.
  • If applicable, other means by which the request for information is being solicited, such as an oral presentation, meeting, telephone survey, electronic media, or any combination of these methods.

(See question No. 12 when issuing an RFI pursuant to the special procedures in section 3-143-614, HAR)

Reference section 3-142-202 (c), HAR

******************Back to Top******************

How often should an RFI be conducted?

An RFI shall be conducted each time an RFP is prepared. Depending on the complexity of the service or the issue being addressed, it may be advisable to conduct more than one RFI for an RFP. For instance, one RFI might be conducted early in the process to obtain feedback on a configuration of services a state agency is considering. After obtaining feedback and analyzing it, a second RFI containing a draft of service specifications may be issued to obtain additional feedback.

Reference sections 3-142-202, and 3-142-302, HAR

******************Back to Top******************

We conducted an RFI, issued an RFP, could not make an award, and plan to re-solicit the services immediately.  Do we need to issue another RFI?

In this case, you would not need to issue another RFI.  However, if you need feedback for any of the modifications, you may want to consider another issuing RFI.

******************Back to Top******************

Is an RFI limited to the competitive (RFP) method of procurement?

No. An RFI can be used with other methods of procurement as well. For instance, if a state agency is contemplating a restrictive purchase of service, issuing an RFI may help to discover whether other providers are interested in providing the service. Note that conducting an RFI without additional efforts/justification is not sufficient for a restrictive purchase of service.

******************Back to Top******************

I heard we could issue an RFI whenever federal funds are involved and not have to conduct an RFP afterwards. Is that true?

No. It is NOT true. Federal funding does not constitute not an exemption from procurement. However, there are times when special procedures may be used. This occurs when a purchasing agency wishes to apply for federal funding that is competitive and there is a requirement/preference that providers be named in the grant application. There is not enough time to issue an RFP from the point at which the grant is announced until proposals/applications are due so special procedures are authorized in section 3-143-614, HAR. A purchasing agency may conduct an RFI in those circumstances. The RFI must include the following:

  • The name of the state agency issuing the request;
  • A statement that the request is being issued for the purpose of including a provider or providers in a federal grant application which may result in a contract with the provider(s) if the state is awarded;
  • A description of the service or services being sought;
  • The criteria by which applicants will be evaluated for selection; The deadline by which responses to the request for information shall be submitted and the method; and
  • Any other requirements that the purchasing agency deems relevant to the request.

Reference: HAR Sections 3-142-202(f) and 3-143-614

******************Back to Top******************

How far in advance of issuing an RFP should we conduct an RFI?

The RFI is for the purpose of obtaining community input whenever an RFP is developed. Depending on the information you are seeking, when the RFP is held may vary (see question 10). Generally, we have found that RFIs held between 2 and 9 months prior to the notice for an RFP tend to be the most useful.

******************Back to Top******************

Does the notice of the RFI  have to include a contact person?

Yes. List the name of the contact person, and contact information (at least phone number, e-mail address, etc.). In order to get quality feedback, respondents will probably need clarification and will have questions.

******************Back to Top******************

I have a document with additional/more specific information that is needed in order to respond to the RFI. How do I make it available?

There are a number of ways you can get additional information to interested parties. You can do any combination of the following.·

  • Post it on your office or department website and indicate the website address in the notice. ·
  • Post it on the Procurement Notices for Solicitation website.  See the Procurement Notices Quick Reference in the PANS Toolbox.
  • Include a name and phone number or e-mail address where they can request the document and you can e-mail it or mail it.

 

******************Back to Top******************

Do RFIs have to have a number and name? Can I use the same number and name as my RFP?

Having an RFI number and name makes it much easier to refer to and find on the PNS. You may have more than one RFI and at times there can be many RFIs on the procurement notices website. You can use the same number as the RFP, but change it a little or make it clearly identifiable that it is an RFI and not an RFP. One way is to include “RFI” in the number.

******************Back to Top******************

When posting on the Procurement Notices for Solicitations website should I indicate that this is an RFI?

Yes! Enter “Request for Information” as the first thing in the description box. If you are attaching a document with additional information, ensure it indicates that it is an RFI at the beginning of the document.

******************Back to Top******************

Should I complete an Attestation Form (SPO-020)?  What should I do with it? Do I need to keep it?

Yes. Place it in your procurement file. Also, print a copy of the notice from the web on the first day it appears, in the same way as you would for a solicitation notice. Keep it in the procurement file. This is part of the documentation.

******************Back to Top******************

I have already posted my notice and a document with additional information. How do I post the agenda for the RFI meeting?

The current procurement notices for solicitation site allows you to post more than one document.

******************Back to Top******************

Where can I see examples of RFIs that were previously conducted?

The Procurement Notices for Solicitations site keeps an archive of recent notices.

******************Back to Top******************

Should a summary of the RFI results be posted?  If yes, does SPO have a website where we can post the results?

Agencies are encouraged to post the RFI results summary on their departmental website.  SPO does not have a site for posting RFI summaries.

******************Back to Top******************

We received a response to our RFI after the submittal due date.  Can we still accept it?

Yes, accept it.  Unlike the RFP process, the RFI is not a formal process.  Although a due date for RFI responses is set, it doesn't prohibit you from accepting responses received after the due date.

 

******************Back to Top******************

 

Are RFI responses public information?

Unless the information provided is confidential or proprietary, the responses are pubic record.

 

 